Wind, sun and storage in one park: Zimbabwe's $300 million hybrid bet
Zimbabwe has never had a utility-scale wind farm. Modaso Energy and Tatanga Energy have announced a $300 million project at Guruve-Mazowe in the north that would be the country's first — 128 megawatts of wind and 100 megawatts of solar, backed by a 50-megawatt battery, generating about 550 gigawatt-hours a year. Standard Bank is lead arranger, with a debt term sheet in place; the state utility ZESA is the intended buyer, though the final power agreement is not yet signed. Financial close is targeted for mid-2027 and operation for 2029, toward Zimbabwe's goal of lifting renewable capacity from 1,282 megawatts in 2024 to 2,640 by 2030. It is a plan, not yet a power station — but a plan with named banks, sites and numbers.